Night walk on the work in progress at Bois Lejuc

As part of the DR0 (preliminary work for CIGÉO), for a few weeks work has begun in the Bois Lejuc.

A “base life” with prefabricated buildings, generators… hosts security guards 24/24, paid to monitor the construction sites [GPS point : 48.516352,5.380570]

Boreholes have started to be drilled [notably here : 48.518185,5.380597], concretely, we can observe tubes (from 1 to 2m) emerging from the ground, surrounded by grillage

Other boreholes are marked by construction cones but not yet drilled

During the day, workers are busy there, at night guards make rounds…

Some traces of passage were left there, despite the presence of nearby security guards and the ban on walking in the Bois Lejuc, we’ll come back!

Note that at other locations in the territory, notably between Bure and Mandres, there are also drillers [for example here : 48.498898,5.374428 and there : 48.495855,5.371767]

All the infos are on this map : http://tinyurl.com/forages-55

08/12/2025

Bois Lejuc
dr0
travaux

Et sinon, 46 jours avant
on écrivait ça
sur le même sujet.

Surprise inspection of the drillings on the rai...

Thursday, October 16, about fifteen people gathered for a surprise visit of the noisy drilling site operated on the old and perhaps future railway line at Menaucourt in the Ornain valley. It is as ...   Lire la suite

CIGEO
travaux

23/10/2025

Et sinon, 2 jours après
on écrivait ça
sur le même sujet.

The DR0 in Interactive Map. Let’s monitor the m...

In an article already published on the Stop CIGÉO Coordination website (in french), a legal analysis of the DR0 file significantly more digestible than the 12,684 pages of the DR0 file from ANDRA w...   Lire la suite

carte
dr0
travaux

10/12/2025